AccountsSkill logo ACCOUNTS SKILL
← SAP Learning Hub🔎 Search all T-Codes

Create Routing in SAP (CA01)

Complete Step-by-Step Guide

Overview

A Routing defines the sequence of operations/work steps required to manufacture a product. It contains work centers, control keys, standard times (setup, machine, labor), and is a key master data for Production Orders, Capacity Planning, and Costing.

Prerequisites

  • Material Master of the header material exists
  • Work Centers are already created (CR01)
  • Plant is defined
  • Authorization for transaction CA01

Step-by-Step Process

1

Enter Transaction Code

Go to transaction CA01 (Create Routing) and press Enter.

2

Initial Screen

  • Material: Enter the material for which you are creating the routing
  • Plant: Enter the plant
  • Key Date: Enter the valid-from date
  • Usage: Enter usage (usually 1 – Production)
  • Press Enter
3

Header Details

  • System proposes Task List Group and Group Counter
  • Enter a short Description
  • Set Status to 4 – Released (important)
  • Enter From Lot Size and To Lot Size if required
  • You can maintain planning and costing relevance
4

Create Operations

  • Go to the Operations overview
  • Enter Operation Number (e.g., 0010, 0020, 0030)
  • Enter Work Center
  • Enter Control Key (e.g., PP01 for internal processing)
  • Enter short text for the operation (e.g., “Cutting”, “Assembly”, “Packing”)
  • Enter Standard Values:
    • Setup Time
    • Machine Time
    • Labor Time
5

Maintain Operation Details (Optional)

  • Double-click an operation to go to details
  • You can maintain:
    • Base Quantity
    • Scrap percentage
    • Activity types
    • Sub-operations
    • Production resources/tools (PRTs)
    • Inspection characteristics (if QM is active)
6

Component Allocation (Optional)

  • You can allocate BOM components to specific operations
  • This controls when components are staged or backflushed
7

Save the Routing

Click the Save button. The Routing is created and can now be used in Production Orders and Production Versions.

Quick Process Flow

CA01 → Material + Plant + Usage → Header (Status = Released) → Operations + Work Center + Times → Save

Common Control Keys

Control Key Description
PP01 Internal processing (most common)
PP02 External processing
PP03 Internal processing with automatic GR
QM01 Quality inspection operation

Related Transaction Codes

T-Code Description
CA01 Create Routing
CA02 Change Routing
CA03 Display Routing
CA11 Create Reference Operation Set
CA21 Create Rate Routing
CR01 Create Work Center
CEWB Engineering Workbench
CA60 Routing Changes
CA80 Work Center Where-Used
Important Notes:
  • Status must be set to 4 – Released, otherwise the routing cannot be used in production orders.
  • Routing + BOM together form the basis of a Production Version.
  • Standard times (Setup, Machine, Labor) are used for scheduling and costing.
  • For process industries, use Master Recipe (C201) instead of Routing.

Helpful Tips

  • Always release the routing (Status 4) after creation.
  • Use meaningful operation short texts for better shop floor understanding.
  • You can copy an existing routing using the “Copy from” function.
  • Maintain accurate standard times for correct capacity planning and product costing.
  • After creating both BOM and Routing, create a Production Version (C223 or in Material Master) for best results.